The Southern Environmental Law Center claims that a planned gas-fired power plant set to power xAI's Colossus II data center will be the largest new source of pollutionThe Southern Environmental Law Center claims that a planned gas-fired power plant set to power xAI's Colossus II data center will be the largest new source of pollution

Mississippi holds hearing on xAI data center amid environmental lawsuit threat

2026/02/18 10:37
2분 읽기

WASHINGTON, US – Mississippi regulators will host a public hearing on Tuesday over plans by Elon Musk’s xAI to build a gas-fired power plant to power its Colossus II data center, as the company faces a lawsuit threat by the NAACP, accusing it of violating federal law by installing and operating gas turbines without air permits.

The civil rights group, acting on behalf of the largely African American local community living near the existing Colossus I facility in Memphis, Tennessee, said xAI began illegally installing and then operating 27 gas turbines at a site in Southaven, Mississippi to power Colossus II, sited across the state line in Memphis.

It said this was being done without properly obtaining the necessary preconstruction or operating air permits required by the Clean Air Act.

Air quality

“Pollution from these turbines is worsening and will continue to worsen the already poor air quality in Southaven, Mississippi and the Memphis metropolitan area,” the NAACP said in a letter declaring its intent to sue xAI.

xAI was not immediately available for comment.

The NAACP said the turbines have the potential to emit a significant amount of smog-forming nitrogen oxides (NOx), above the Clean Air Act’s “major source” threshold, and other pollutants including fine particulate matter and carcinogenic formaldehyde, harming largely African American local communities.

The Clean Air Act requires plaintiffs to signal their intent to sue 60 days in advance.

xAI has been rapidly building its Colossus supercomputer which is being used to train the company’s Grok AI chatbot in Memphis and expanding to Southaven. It is currently in phase 2 and is seeking to begin a third phase soon.

After the Southern Environmental Law Center (SELC), which is representing the NAACP in this new lawsuit threat, filed an intent to sue xAI in 2024 for installing 35 non-permitted turbines at its Colossus 1 site, the company removed 20 turbines and obtained permits for the remaining 15.

The Mississippi Department of Environmental Quality hearing is the only chance for the public to weigh in on the project, which SELC has said will be the largest new source of pollution in the area around Memphis in years.

The DEQ said xAI has submitted permit applications for 41 permanent turbines at the site and will run a number of temporary turbines while the applications are being reviewed. – Rappler.com

시장 기회
Xai 로고
Xai 가격(XAI)
$0.01068
$0.01068$0.01068
+0.75%
USD
Xai (XAI) 실시간 가격 차트
면책 조항: 본 사이트에 재게시된 글들은 공개 플랫폼에서 가져온 것으로 정보 제공 목적으로만 제공됩니다. 이는 반드시 MEXC의 견해를 반영하는 것은 아닙니다. 모든 권리는 원저자에게 있습니다. 제3자의 권리를 침해하는 콘텐츠가 있다고 판단될 경우, [email protected]으로 연락하여 삭제 요청을 해주시기 바랍니다. MEXC는 콘텐츠의 정확성, 완전성 또는 시의적절성에 대해 어떠한 보증도 하지 않으며, 제공된 정보에 기반하여 취해진 어떠한 조치에 대해서도 책임을 지지 않습니다. 본 콘텐츠는 금융, 법률 또는 기타 전문적인 조언을 구성하지 않으며, MEXC의 추천이나 보증으로 간주되어서는 안 됩니다.