Company Achieves ~2.8 EH/s with a 110 MW Expansion Well Underway VANCOUVER, BC, Jan. 27, 2026 /PRNewswire/ — Bitzero Holdings Inc., (CSE: BITZ.U) (OTCQB: BTZRF) (Company Achieves ~2.8 EH/s with a 110 MW Expansion Well Underway VANCOUVER, BC, Jan. 27, 2026 /PRNewswire/ — Bitzero Holdings Inc., (CSE: BITZ.U) (OTCQB: BTZRF) (

Bitzero Holdings Inc. Shares Operational Update

2026/01/27 19:46
4 min read
For feedback or concerns regarding this content, please contact us at [email protected]

Company Achieves ~2.8 EH/s with a 110 MW Expansion Well Underway

VANCOUVER, BC, Jan. 27, 2026 /PRNewswire/ — Bitzero Holdings Inc., (CSE: BITZ.U) (OTCQB: BTZRF) (FSE: 000) (“Bitzero” or the “Company”), a provider of sustainable blockchain and high-performance compute (HPC) data center infrastructure, today announced an operational update of the Company’s self-mining operations.

Since last reported in September 2025, the Company has significantly increased its hashrate to approximately 2.80 EH/s, compared to 1.76 EH/s previously reported, representing an increase of approximately 59%. At this operating level, the Company is currently receiving approximately 1.1 bitcoin per day, subject to network conditions. This improvement, together with the Company’s previously announced reduction in energy costs following the execution of new power purchase agreements, enhances the Company’s operating profile and is expected to support improved revenue generation and profitability. As previously reported, the Company’s operations are currently supported by a blended power cost of approximately US$0.03–0.035 per kWh.

As previously announced, Bitzero remains on track to enter the next phase of expansion which is expected to deliver a total of approximately 110 MW of energized capacity by Q4 2026. Based on current forecasts, this level of capacity could support ~10.0 EH/s if fully allocated to Bitcoin mining. A further potential expansion phase is planned for completion by Q4 2027 and would increase total energized capacity to approximately 325 MW if completed as contemplated. A fully dedicated 325 MW of capacity to Bitcoin mining could support up to ~ 30.0 EH/s.

“The steady growth of our compute power is a direct reflection of our disciplined execution and long-term strategy,” said Mohammed Bakhashwain, CEO and President of Bitzero. “With our expansion well underway, we’re scaling efficiently, strengthening our infrastructure, and positioning the company to capture meaningful value as the Bitcoin network continues to evolve.”

To learn more about Bitzero’s sites, visit www.bitzero.com.

Energy Costs

Metric 

Bitzero

Energy Cost kWh (Dec 2025)

0.04 US$/Kwh

Daily Energy Cost (Dec 2025)

US$38,400

Mining Monthly Metrics 

Bitzero Holdings Inc. 

Dec-25

Monthly Total Hash Rate EH/s 

2.45

Average operational Hash Rate EH/s 

2.37

Bitcoin Mined 

29.31

Bitcoin Mined Per 1EH/s 

12.37

Bitcoin Mined Per Day

0.95

Bitcoin Mined Per Day Prior Month

0.72

Bitcoins mined per EH/s 

JAN 

FEB 

MAR 

APR 

MAY 

JUN 

JUL 

AUG 

SEP 

OCT 

NOV 

DEC 

EH/s 

1.18

1.33

1.35

1.38

1.41

1.42

1.36

1.36

1.76

1.85

1.85

2.45

Bitcoins mined  

21.24

21.00

22.79

21.82

22.84

21.22

21.67

21.30

23.85

22.70

21.46

29.31

Bitcoins mined per EH/s 

18.08

15.81

16.89

15.80

16.22

14.94

15.91

15.64

13.55

12.27

11.60

11.97

About Bitzero Holdings Inc.

Bitzero Holdings Inc. is a provider of IT energy infrastructure and high-efficiency power for data centers. The Company focuses on data center development, Bitcoin mining, and obtaining strategic data center hosting partnerships. Bitzero Holdings Inc. now has four data center locations in the North American and Scandinavian regions, powered by clean, low-carbon energy sources. Visit www.bitzero.com for more information.

Bitzero Contact
Mohammed Bakhashwain
+44 777 303 0394
[email protected]

Bitzero Press Contact
[email protected]

Forward-Looking Information

This news release contains “forward‑looking information” within the meaning of applicable Canadian securities laws, including statements regarding the Company’s projected energized capacity at Namsskogan, Norway; expected timing for completion of expansion phases (Q4 2026 and Q4 2027); potential hashrate at various capacity levels (including ~10 EH/s and ~30 EH/s) if fully allocated to Bitcoin mining; and anticipated operating efficiencies, power costs and their impact on revenue generation and profitability. Forward‑looking information is based on management‘s current expectations and assumptions, including with respect to construction timelines, availability and performance of mining equipment, network difficulty, Bitcoin price, power availability and pricing, curtailment, uptime, regulatory approvals and general economic conditions.

Forward‑looking information is inherently subject to known and unknown risks and uncertainties that may cause actual results to differ materially from those expressed or implied, including risks related to construction and commissioning, supply chains, equipment performance, power markets and curtailment, permitting and regulatory matters, digital asset price volatility, network difficulty, cybersecurity, financing, and other factors described under “Risk Factors” in the Company‘s public filings. Readers are cautioned not to place undue reliance on forward‑looking information. The Company undertakes no obligation to update any forward‑looking information except as required by applicable securities laws.

Neither the Canadian Securities Exchange nor its Regulation Services Provider accepts responsibility for the adequacy or accuracy of this release.

Cision View original content to download multimedia:https://www.prnewswire.com/news-releases/bitzero-holdings-inc-shares-operational-update-302670675.html

SOURCE Bitzero

Disclaimer: The articles reposted on this site are sourced from public platforms and are provided for informational purposes only. They do not necessarily reflect the views of MEXC. All rights remain with the original authors. If you believe any content infringes on third-party rights, please contact [email protected] for removal. MEXC makes no guarantees regarding the accuracy, completeness, or timeliness of the content and is not responsible for any actions taken based on the information provided. The content does not constitute financial, legal, or other professional advice, nor should it be considered a recommendation or endorsement by MEXC.
Tags:

You May Also Like

UK and US Seal $42 Billion Tech Pact Driving AI and Energy Future

UK and US Seal $42 Billion Tech Pact Driving AI and Energy Future

The post UK and US Seal $42 Billion Tech Pact Driving AI and Energy Future appeared on BitcoinEthereumNews.com. Key Highlights Microsoft and Google pledge billions as part of UK US tech partnership Nvidia to deploy 120,000 GPUs with British firm Nscale in Project Stargate Deal positions UK as an innovation hub rivaling global tech powers UK and US Seal $42 Billion Tech Pact Driving AI and Energy Future The UK and the US have signed a “Technological Prosperity Agreement” that paves the way for joint projects in artificial intelligence, quantum computing, and nuclear energy, according to Reuters. Donald Trump and King Charles review the guard of honour at Windsor Castle, 17 September 2025. Image: Kirsty Wigglesworth/Reuters The agreement was unveiled ahead of U.S. President Donald Trump’s second state visit to the UK, marking a historic moment in transatlantic technology cooperation. Billions Flow Into the UK Tech Sector As part of the deal, major American corporations pledged to invest $42 billion in the UK. Microsoft leads with a $30 billion investment to expand cloud and AI infrastructure, including the construction of a new supercomputer in Loughton. Nvidia will deploy 120,000 GPUs, including up to 60,000 Grace Blackwell Ultra chips—in partnership with the British company Nscale as part of Project Stargate. Google is contributing $6.8 billion to build a data center in Waltham Cross and expand DeepMind research. Other companies are joining as well. CoreWeave announced a $3.4 billion investment in data centers, while Salesforce, Scale AI, BlackRock, Oracle, and AWS confirmed additional investments ranging from hundreds of millions to several billion dollars. UK Positions Itself as a Global Innovation Hub British Prime Minister Keir Starmer said the deal could impact millions of lives across the Atlantic. He stressed that the UK aims to position itself as an investment hub with lighter regulations than the European Union. Nvidia spokesman David Hogan noted the significance of the agreement, saying it would…
Share
BitcoinEthereumNews2025/09/18 02:22
Things No One Told You About White Label Crypto Exchange Software

Things No One Told You About White Label Crypto Exchange Software

White Label Crypto Exchange Software The cryptocurrency market continues to attract entrepreneurs and businesses looking to build new revenue streams. For
Share
Medium2026/04/03 14:36
The Architect’s Reflection: The 5D Middleware

The Architect’s Reflection: The 5D Middleware

09:00 | The Pulse Audit (Curing the Static Profile) I spent the morning auditing a “Static Dump” from a 2026-era database. It was a graveyard of “Profiles” — frozen
Share
Medium2026/04/03 14:36

Trade GOLD, Share 1,000,000 USDT

Trade GOLD, Share 1,000,000 USDTTrade GOLD, Share 1,000,000 USDT

0 fees, up to 1,000x leverage, deep liquidity